Officials In Action – East Ave

On January 26th, Council-members Kydes and Maggio introduced a resolution requesting the the state revisit the planned bridge clearance.

Resolution-January 26 2016 meeting

After objections to the traffic study at $39k, the current proposal for a significant scoping change, and at a cost of almost ten times as much ($359k) appeared on a Public Works agenda for January 5th.

http://www.norwalkct.org/ArchiveCenter/ViewFile/Item/10156

On November 30, the council had a TRAFFIC STUDY (not an ENGINEERING CONTRACT to alter the 2010 plan by removing a third of the length and changing the lane configuration again) that would have cost $39k.

http://www.norwalkct.org/ArchiveCenter/ViewFile/Item/10062